Completed 2007
Timken Plant - Buss & Substation - Cairo, GA
Installed electrical portion of a new 12,470 volt substation and 800 amp 480 volt buss duct installation.
GA Pacific - Lime Mud Dryer - Cedar Springs, GA
Project consisted of installing 2,000 feet of various size stainless steel cable trays with supports, over 150,000 feet of tray cable, one new control panel, ten new drives and 110 instruments. Also wired 26 new motors and rewired existing Honeywell instruments.
Ga Pacific - Store Room - Cedar Springs, GA
Project consisted of roughly 1,500 lf of conduit and 4,000 lf of cable. We also installed three 480v panels, 3 transformers, and 60 high bay lights.
ConAgra - Roaster - Sylvester, GA
Installed electrical to roaster and all associated equipment.
Completed 2006
Ga Pacific- Pulpmill Reinstrumentation - Cedar Springs, GA
Installed new stainless steel trays, pulled 450,000 feet of IAC cable, Installed 96 new instruments, terminated all plc, DCS, and Honeywell equipment, commissioned and put on line.
Propex Inc. - New Security System - Nashville, GA
Installed modifications to entrance gate system, including foundations, electrical service, and gate installations. Installed security card systems at all entrance doors and security cameras.
Propex Inc. - Loom Equipment Relocation and Installation - Roanoke, AL
Handled removal, transportation, and installations of looms. Installed new support structure, electrical and mechanical piping services.
Mokawk - Equipment Projects, Mechanical and Electrical Support Services - Roanoke, AL
Assisted plant with various equipment projects, fabrication and installation of equipment parts, supported plant with equipment installations and start-up.
Alpha 7 Gypsum - Design - Build Gypcrete plant - Fairburn, GA
Designed and installed the electrical system for a new process plant in the Gypsum industry. Power, lighting, controls and stand-by power were installed. Performed mechanical installation of equipment, boiler, air compressor and silos for the process.
|